Buyer profile
THE PIRBRIGHT INSTITUTE
Get alerts when THE PIRBRIGHT INSTITUTE publishes a new tender — 7-day free trial, then £4.99/month.
Total contracts
63
Known spend
£5m
48 disclosed
Average value
£105,006
Per contract
Active suppliers
10
Last 5 years
Top suppliers
Last 5 years- 1
SCHNEIDER ELECTRIC LIMITED
£104,818
- 2
Luhrfilter Ltd
2 winslatest 07 May 2026£293,500
- 3
BECKMAN COULTER UNITED KINGDOM LIMITED
£282,000
- 4
CJB Commissing Services
2 winslatest 13 Jan 2026£84,810
- 5
Terra-NRG Ltd
2 winslatest 05 Jun 2026£83,189
- 6
Safety Gas Detection Limited
2 winslatest 29 Jun 2026£82,046
- 7
Fuel Conservation services Ltd
£267,995
- 8
Lifescience Technology Ltd
£255,000
- 9
Walker Safety Cabinets Ltd
1 winlatest 03 Sept 2025£170,265
- 10
Global Life Sciences Solutions Operations UK Ltd
1 winlatest 17 Jun 2025£154,360
What they buy
By CPV categoryNo CPV data captured yet for this buyer.
Tender activity
Notices published per month — last 24 months
All contracts (63)
Site steam upgrade project - principal contractor & installation package
The purpose of this project is to increase the Institute’s sustainability (both environmental & financial), reduce carbon emissions and safeguard the steam supply to all buildings
Biological safety cabinet (bscs), fume cupboard (FC), laminar flow cabinets (lfcs) & PCR workstation maintenance contract – the pirbright institute
The contract is for a single supplier to provide Biological Safety Cabinet (BSCs), Fume Cupboard (FC), Laminar Flow Cabinets (LFCs) & PCR Workstation Maintenance - at The Pirbright
Condenser fan replacement - biggs building chiller
Replacement condenser fans so that the Biggs Chiller can operate and provide free cooling to Biggs and when required can also supply chilled water to ISO11. We have found out that
ISO 11 incinerator life extension project – WP9 primary catch box upgrade
The contract is for a single supplier to provide Build of Work Package 9 - Primary Catch Box Upgrade, as per the Detailed Design for The Pirbright Institute (Pirbright), Ash Road,
Brooksby building incinerator - re-testing and commissioning of the incinerator's BACS alarms points
Brooksby Building Incinerator - final commissioning and testing of the existing incinerator BACS points is required to ensure the incinerator plant is fully connected to the site-w
Renewal of service contract for the power back-up generator control systems for plowright and the energy centre (EC1)
Maintenance of generator control systems equipment including an exact mock-up of the control systems so that install upgrades and new parts can be tested these before added to our
Site steam upgrade: phase 2 project - project management and detailed design.
The contract is for a single supplier to provide Project Management and Detailed Design in relation to the Site Steam Upgrade project at The Pirbright Institute, Ash Road, Pirbrigh
Site HV/LV supplies maintenance
The contract is for a single supplier to provide Site HV/LV Supplies Maintenance - at The Pirbright Institute, Ash Road, Pirbright, Surrey, GU24 0NF. The HV/LV engineers will be re
Linkedin recruitment job board licenses renewal
LinkedIn Recruiter has proven to be the most effective and reliable tool for the Talent Acquisition team at Pirbright in driving direct sourcing strategies and supporting external
Controls and BMS package to enable the operation and monitoring of the CHP LTHW heat recovery system
The CHP LTHW Heat Recovery Project is to enable heat generated from the CHP as low temperature hot water to offset steam production used for heating and hot water within the Plowri
Modifications and upgrades to existing site generator to be used for brooksby building
Modification and upgrade works to ensure suitable remote conditional monitoring via installation of a new control system to existing site. This will ensure capability to monitor an
Brooksby incinerator phase 1 - testing and investigation
Procurement of a contractor with experience of incinerator systems is required for Phase 1 - Testing and Investigation works. The scope of works for Phase 1 is detailed below: • Sy
Procurement recommendation to award document reporting, news, and education services
Reporting, News, and Education Service" Diligent service Agendas, minutes, and supporting documents for meetings are shared through secure platform due to the sensitive nature of t
Provision of facilities management of soft services to offices, laboratories, and associated buildings at the pirbright institute
Waste Prevention and Management. Waste container types. The Contractor shall advise the Pirbright Institute on the full range of waste container types available and make recommenda
Safety instrumented function (SIF) to detect imminent flooding of the brooksby building.
As part of the Brooksby project, in order to be compliant with Functional Safety standards (IEC 61508/61511), services are required to purchase materials, manufacture a panel, inst
Dynamic light scattering machine
As a first step towards evaluating the use of RNA vaccines for livestock, the Centre for Veterinary Vaccine Innovation and Manufacturing (CVIM) collaborated to carry out a proof-of
Formulation machine
As a first step towards evaluating the use of RNA vaccines for livestock, the Centre for Veterinary Vaccine Innovation and Manufacturing (CVIM) collaborated ) to carry out a proof-
Annual maintenance contract of sitewide traka key cabinets.
The TRAKA System in the Pirbright Institute is Obsolete and this is to provide Extended Support to Supply parts, Maintain the System and Renew Concurrent Users License and ensure t
ISO 11 incinerator life extension: WP2 control panel control hazop items to reduce operational risk to
The ISO 11 Incinerator was installed within the "Postmortem - Incinerator" (PMINCIN) building circa 1994/95 and much of the original plant remaining has now reached the end of its
Brooksby occupational support