System operational · UK tenders

Procurement Act 2023 notices · UK10

UK10 contract change notice

Published before changing a contract's value or term, or if it is transferred due to corporate restructuring.

When it is published

For contracts over £5 million, before or after the change, the modified contract document, redacted as necessary, must be attached within 90 days of the change. Not required for defence and security contracts, light-touch contracts, private utilities, or if Northern Irish rules apply. Attaching the modified contract is not required if Welsh rules apply.

What it means for suppliers

A change notice often means an extension or a bigger contract, which can push back the re-tender you were waiting for. Check your pipeline whenever one appears on a contract you are tracking.