GB-Edinburgh: Refurbishment & Upgrade of Stoer Head Lighthouse
Northern Lighthouse BoardEstimated Value
Up to £88,024
Deadline
4 November 2016
Published
18 November 2016
Type
works
Overview
Refurbishment & Upgrade of Stoer Head Lighthouse PRE-START 1. In advance of the start of site project works by the Principal Contractor shall arrange an initial Asbestos Survey and Report via a UKAS accredited asbestos surveying company prior to refurbishment works starting on site.
STAGE 1 2. The Principal Contractor will establish temporary welfare and storage in agreed areas.
The Principal Contractor shall provide all drinking water and non-potable water for the site works. 3. The Principal Contractor will establish a temporary navigational light on the balcony as per NLB electrical specifications to meet an NLB / Contractor mutually agreed Notice to Mariners date for the temporary light to come into operation. 5.
Contact & helpdesk
Please contact Ruth Millan, Procurement@nlb.org.uk to confirm attendance and names of representatives attending site.
Additional details
After removal of all de-commissioned NLB equipment (i.e) Optic Control Cubicle, old batteries, etc), provide appropriate safe packaging and arrange for land transportation to NLB Oban Depot for removal of NLB spares and disposal to registered dumps as required. De-mobilise and clear site. 6.
Principal Contractor to supply the NLB Project Engineer with ‘as built’ information of the electrical installation for incorporation within NLB Operation and Maintenance Manual documentation. STAGE 2 7.
A new toilet compartment is to be created in the ground floor of the tower. Connections shall have to be made for bring a new water supply in from by the bothy and foulwater connection into the existing outfall via a new manhole.
Following the digging of the trenches for the connections, the courtyard will have to be reinstated to the present condition. The new toilet will be installed with a macerator. 8.
A new hinge table has to constructed and mounted to the tower wall to provide a temporary rest area for NLB technicians. 9. Following the re-engineering works general painting and refurbishment of the internal and external areas of the tower is required as per Specifications.
Temporary Scaffolding, power cradle, or other safe working measures are to be supplied by the Contactor for working at height. The nominated painters shall have to provide evidence of competence and experience of painting in a similar exposed environment. 10.
De-mobilise and clear site of all ex. project materials and plant for safe delivery back to Oban, Contactors premises or disposal to registered dumps. 11. Principal Contractor to supply the NLB Project Engineer with ‘as built’ information for incorporation within NLB Operation and Maintenance Manual documentation.
Site visits will be conducted on 17 August 2016. Additional information: The contracting authority considers that this contract may be suitable for economic operators that are small or medium enterprises (SMEs).
However, any selection of tenderers will be based solely on the criteria set out for the procurement. The tender documents can be downloaded from our buyer profile http://nlb.g2b.info, other information.
AI AnalysisMembers
Requirements, key tasks and tips for reading this tender — included with Tendarix membership.
£4.99/month after a 7-day free trial. Cancel anytime before it ends and you pay nothing.
Before you bid, buyers check
two years of filed accountsyour financial standingturnover vs contract valueyour Companies House recordcash flow for 30-day termscredit scores and ratios
Actions
Start free trialto open noticeCreate an account and start a 7-day free trial to open the buyer’s own notice and tender documents, plus fit scoring and the Bid Writer. Then £4.99/month — cancel anytime.
Open Bid WriterIndependent software, web & cloud studio. We design, build and grow digital products that quietly outlast their category.
How to Apply
Step-by-step submission guide
Submission Portal
Contracts Finder
Open the original notice
Click the button below to view this tender on Contracts Finder
Find the submission method
Look for "How to apply" section — most tenders link to an eSourcing platform (e.g. In-Tend, ProContract, Jaggaer)
Create an account
Register on the eSourcing platform for free — you'll need a company email and DUNS number
Download tender documents
Download the ITT (Invitation to Tender), specification, pricing schedule, and any templates
Submit your response
Upload completed documents through the portal before the deadline — late bids are automatically rejected
Most buyers do NOT accept email submissions. You must submit through their eSourcing platform. Check the notice for the exact link.
Buyer Profile
Northern Lighthouse BoardKey Dates
Published
18 November 2016
Submission deadline
4 November 2016
Notice type
award
Source
contracts finder
Related Tenders
Framework agreement for design, supply & installation of kitchens (lot 1) and bathrooms (lot 2) & associated works 2026 to 2030
This framework contract lets suppliers provide design, supply and installation services for kitchen and bathroom upgrades in public buildings from 2026 to 2030, covering everything from cabinets and worktops to showers and LED lighting.
Joinery contractors framework
NHS Lanarkshire is setting up a Joinery Contractors Framework to supply planned, routine, reactive and emergency joinery work across its hospitals and community sites. The contract is split into three lots based on work value and location, with one‑year emergency cover required.
Angus rural mobility hub - enabling infrastructure works
The project comprises the enabling infrastructure only required for a new Mobility Hub. We are seeking a Main/ Principal Contractor to carry out the enabling infrastructure works f
Provision of motor control centres, systems integration and ICA services
Scottish Water is seeking to establish a multi-supplier Framework Agreement for the provision of Motor Control Centres (MCCs), Instrumentation, Control and Automation (ICA), System