Buyer profile
LONDON GATEWAY PORT LIMITED
Get alerts when LONDON GATEWAY PORT LIMITED publishes a new tender — 7-day free trial, then £4.99/month.
Total contracts
21
Known spend
£283m
15 disclosed
Average value
£19m
Per contract
Active suppliers
10
Last 5 years
Top suppliers
Last 5 years- 1
GOBION CONSTRUCTION LTD
£52m
- 2
BoxBay FZCO
1 winlatest 18 Jul 2025£92m
- 3
Jan De Nul nv
1 winlatest 14 Oct 2025£57m
- 4
Goldbeck Construction Limited
1 winlatest 23 Jul 2025£11m
- 5
Cullen Grummitt & Roe (UK) LTD
1 winlatest 16 Oct 2025£6m
- 6
RYEBRIDGE LIMITED
£2m
- 7
Terberg Benschop B.V.
1 winlatest 23 Sept 2026£2m
- 8
Houcon Cargo Systems b.v
1 winlatest 21 Jan 2026£2m
- 9
Movella Oy
1 winlatest 12 Jun 2026£1m
- 10
OCS Group UK Ltd
1 winlatest 01 Apr 2026£452,000
What they buy
By CPV categoryConstruction worksCPV 45
2 contracts
Business servicesCPV 79
1 contract
Tender activity
Notices published per month — last 24 months
All contracts (21)
Purchase of 10 x hydraulic trailers
The trailers have to meet the following capabilities: a) Ground Clearance >150mm b) Steering Angle Requirement > +/-13º c) Load bed length 12180mm d) Load capacity 70ton e) Dead we
Boxbay enabling civil works
The enabling works consist of the installation of new below ground utility ducting; new fire water pipework; new fire hydrants; and new drainage pipework along with associated acce
London gateway berth 5 structured cabling system
This document is issued as part of the Request for Information (RFI) / Pre-Qualification Questionnaire (PQQ) stage and seeks to obtain information from suitably qualified suppliers
London gateway - boxbay main works
The BOXBAY Works at the existing MT Park area of London Gateway comprise the demolition of existing below-ground services and the construction of the substructure, superstructure a
Catering services tender
London Gateway Port requires catering services to provide its staff and visitors with breakfast, lunch and snack offerings across its shifts that operate 24/7. There are 2 main sit
London gateway berth 5 container yard construction
London Gateway (LGW) is planning to develop a container storage yard at London Gateway Port. The yard is located at Berth 5 of the Port. The Works include, but are not limited to,
London gateway - second rail terminal phase 2
DP World is undertaking the expansion of its London Gateway Port facility at Stanford le Hope, through the development of a new second rail terminal located to the west of the exis
New radio system
London Gateway has expansion plans recently backed by a billion-pound investment from DP World, along with various government backed initiatives to develop the surrounding area. Fo
Purchase of heavy duty container cassettes
Purchase of 100 heavy duty container cassettes for London Gateway Port a) Weight of Heavy-Duty Cassettes (Max 4500kg) b) Load capacity (max 62,000 kg) c) Dimensions : Overall width
C2526 maintenance dredging - 2025 campaign
To ensure deep draft vessels can continue to access London Gateway Port, Maintenance Dredging of the part of the Navigation Channel and berth pocket is required. The Works require
Engineering consultancy services for design & construction of the boxbay empty superstack
The HBS will be a BoxBay empty superstack for storage of containers, which is positioned between the existing Berths 3 and 4 that are already in operation. CGR to undertake the eng
Maintenance dredging channel
London Gateway Port Limited (LG) is a statutory Harbour Authority by virtue of the London Gateway Port Harbour Empowerment Order 2008 (the HEO) which allows for the construction an
Construction of multi-use amenity hub and sports facility(the hive)
DP World is the owner and operator of London Gateway, a strategic port and logistics facility in Thurrock, United Kingdom. The site comprises a deep-sea container port, rail termin
Contract C2547 - construction of berth 6 east container storage yard
Development of a container storage yard at London Gateway Port. The yard is located at Berth 6 of the Port, to the east of existing Berth 6 North and South Storage Yard. The total
Design & construction of the boxbay empty superstack
The highbay stack system ("HBS") will be a BoxBay empty superstack for storage of containers, which is positioned between the existing Berths 3 and 4 that are already in operation
Design, supply, installation, commissioning, and maintenance of shore power infrastructure at london gateway and DP world southampton
Shore-to-Ship Power (SSP)-also known as Cold Ironing or Alternative Maritime Power (AMP)-is a system that allows ships docked at port to plug into the local electrical grid and tur
Security services at london gateway port and southampton
Security services contract at DP World London Gateway and DP World Southampton Security Services - A range of security operations involving SIA licensed security guards are require
Supply OF 10 RORO terminal tractors
Supply of 10 x RORO Terminal Tractors, with the following capabilities - a) >95,000kg GCW b) Preparation for hydraulic trailer operation (200Bar output) c) Hybrid and/or NRE diesel
Design and supply of 12 x megawatt DC fast chargers
The works comprise of the design and supply of 12 x Megawatt DC Fast Chargers for Straddle Carriers
Training and development partner - the hive, multi-purpose amenity facility
DP World the owner and operator of London Gateway Port Limited is seeking Expressions of Interest from companies, organizations and consortiums interested in acting as a partner an