If you run a small building firm, a specialist trade or a facilities management (FM) business, public work can fill your order book for years. It can also swallow weeks of unpaid bid time. This guide helps you decide where to look, which rules protect you and what to have ready before you bid.

It covers construction and FM together, because similar buyers and rules apply. It reflects the position on 21 October 2026, and ends with a checklist to run each notice through. The Procurement Act 2023 has applied to new procurements since 24 February 2025. Devolved Scottish authorities keep their own rules.

Key figures

Who buys construction and FM work

The government's FM standard says the public estate holds over 300,000 properties. Here are five buyer groups to know.

The thresholds that matter to small contractors

Most small jobs sit below the works threshold. The full Act covers works contracts worth £5,193,000 or more including VAT. For goods and services the figures are £135,018 for central government and £207,720 for other buyers. The regulations list works activities by CPV code, all in division 45, construction work. That includes roof repair and heating-plant repair. Repair and maintenance services in division 50 are not on the list, so read the codes in the notice.

Below the thresholds, lighter rules apply. Take a council that advertises £150,000 of roof repairs. That is below the £207,720 line for councils. So the council cannot shortlist you on experience, accounts or technical ability before it invites tenders. Buyers must also consider the barriers that small firms face. NHS trusts count as central government for these figures. Framework call-offs, schools, devolved Welsh authorities and transferred Northern Irish authorities follow different rules.

If a buyer advertises a contract, it must publish a below-threshold tender notice first. This applies from £12,000 (central government) or £30,000 (other buyers). A buyer can still ask a closed group, such as a framework, for quotes without advertising. So a place on a framework or approved list is worth winning. If a council reserves a contract for local firms, the notice must say so.

Where the full Act applies, a buyer cannot make you hold contract insurance before award. It can ask for proof that cover will be in place when the contract starts. It can still require insurance the law demands, such as employers' liability. Authorities expecting to spend over £100 million in a year must list planned contracts above £2 million up to 18 months ahead.

Health and safety under CDM 2015

The Construction (Design and Management) Regulations 2015 have applied in Great Britain since 6 April 2015. They give duties to clients, designers, principal designers, principal contractors, contractors and workers. If your job has one contractor, you prepare the construction phase plan. If it has several, the principal contractor does (HSE summary of duties).

Commercial clients must give every bidder pre-construction information, so ask for it. Expect tender questions on how you plan, manage and monitor risk. The Construction Playbook puts health and safety among its top priorities.

Questionnaires and accreditation

Older construction questionnaires used PAS 91. BSI withdrew PAS 91 on 21 April 2023. The Common Assessment Standard (CAS) from Build UK now fills that role. Its question set includes the key questions from the standard selection questionnaire and PAS 91.

A Recognised Assessment Body certifies you once a year, at desktop or site-based level. Build UK lists seven such bodies, and Version 6 is due on 1 November 2026. Government guidance lets buyers keep using CAS for works if their conditions are proportionate. Where the full Act applies, buyers also cannot require audited accounts unless the law already requires you to have them. Our guide to Constructionline, CHAS and Achilles covers the schemes and their costs.

Build UK says a CAS certificate meets stage one of pre-qualification. CAS also has a building safety section. Find a Tender separately stores your core company details, which you share with a code. Keep them accurate.

The Playbook, social value and building safety

The Construction Playbook sets 14 key policies for buying public works. Central government departments and their arm's length bodies follow it on a "comply or explain" basis. It tells buyers to publish pipelines that look three to five years ahead.

Central government must also weigh social value on above-threshold procurements. PPN 002 sets a minimum of 10% of the score. For procurements started from 1 January 2027, PPN 026 sets minimums of 10% from £1 million and 20% from £5 million. Councils and other buyers are not bound by these notes, but most must have regard to the National Procurement Policy Statement. It covers social value and a fair chance for small firms.

The Building Safety Act 2022 created the Building Safety Regulator. In England, building work on a higher-risk building needs the regulator's approval first. Exempt work, competent person scheme work and emergency repairs are excluded. Higher-risk buildings are at least 18 metres tall or seven storeys high. They hold two or more homes, or are a hospital or care home. Part 2A of the Building Regulations 2010 sets competence duties for all building work in England, plus extra duties for higher-risk work. Where more than one contractor will work on a project, the client must appoint a principal designer and principal contractor in writing.

Getting paid: terms, retentions and disputes

Valid, undisputed invoices on a public contract must be paid within 30 days of receipt. Regulated below-threshold contracts carry the same term. Both reach sub-contracts, so a main contractor owes you the same 30 days. Contracts awarded by a school are not covered. Central government buyers are expected to spot check payments down the chain on new contracts worth over £5 million a year, advertised from 1 October 2025.

The prompt payment policy page says interest on late payment is not paid automatically, so claim it. It also names the Public Procurement Review Service as a route for payment complaints. If you hold a construction contract in Great Britain, the Construction Act lets you refer a dispute to adjudication at any time.

The government's Commercial Payments Bill would ban withholding retention sums under construction contracts. It is not law yet and now goes to the Commons. The ban would take effect two years after a start date that ministers set by regulations. Until then, check what each contract holds back and for how long.

Facilities management: hard and soft services

The government's FM standard splits FM in two. Hard services cover fixed parts of a building, such as repairing a roof or servicing a boiler. They include checks on asbestos, fire risk, fixed wiring, gas and water hygiene, plus mechanical, electrical and fabric maintenance. Soft services are delivered at the building, such as cleaning, pest control, catering, waste and security.

The Government Commercial Agency, which replaced Crown Commercial Service, runs agreement RM6378, Facilities Management and Security Services. Its contract details notice lists total, hard and soft FM lots for contracts up to £2 million a year. Those lots have 37, 58 and 35 suppliers. RM6378 is an open framework, so a further award must happen within three years of the first award in August 2026. New suppliers can bid then. NHS SBS Hard FM3 has specialist lots such as roofing, boilers and fixed wiring testing. Our guide to frameworks explains how they work.

Staff often move when an FM contract changes hands. TUPE covers cleaning moving to a contractor, or a contract passing to a new one. In Great Britain, the outgoing employer must normally give the new employer employee liability information at least 28 days before the transfer. That is usually after award, so ask the buyer for staff data at clarification stage and price from it. Our TUPE guide explains the process.

Here is a simple route in.

  1. Pick your lane. Hard, soft or total FM decides which lots fit.
  2. Match the value band. Start with lots up to £2 million a year.
  3. Cost the staff. Build TUPE and pay costs into your price.
  4. Offer subcontract help. If a lot is closed to you, ask appointed suppliers for work.

Your readiness checklist

Run every notice through this table before you commit bid time.

AreaWhat the buyer may checkWhat to have ready
Health and safetyHow you plan and control riskPolicy, sample construction phase plan, accident record, CAS or equivalent certificate
InsuranceCover for the contractCurrent certificates, or an insurer's letter confirming cover from the start date
Building safetyCompetence for design and building workNamed lead, training records, higher-risk building experience if relevant
Supplier recordCore company detailsCompleted Find a Tender supplier information and a current share code
Supply chain30-day payment down the chainYour own payment terms with subcontractors and suppliers
Social valueMeasurable local benefitApprenticeships, local spend and jobs you can deliver and report
Staff (FM bids)TUPE and pay costsStaff data request, pay bands and on-costs
Track recordSimilar workThree case studies with values, dates and referee details

Common mistakes to avoid

  • Citing PAS 91. It is withdrawn. Use CAS, or ask which certificate the buyer will accept.
  • Buying insurance too early. Where the full Act applies, a buyer cannot require contract insurance before award. Offer an insurer's letter first.
  • Ignoring retentions in your cash flow. Ask what the contract holds back and plan for it.
  • Pricing FM without TUPE data. Staff costs can decide the contract, so ask for staff data early.

Frequently asked questions

Do I need CAS or Constructionline to bid?

Not by law. Buyers may ask for CAS and can keep using it on works, but their conditions must be proportionate. If a tender names one scheme, ask through clarifications whether equivalent evidence will do.

Can a council limit a tender to local firms?

In England it can, for below-threshold contracts only. The council must say so in the notice and state the local area.

Are retentions banned?

Not yet. The Commercial Payments Bill would ban them in construction contracts, but it has still to pass the Commons. The ban would take effect two years after a start date set by regulations. Check what your contract holds back.

Which threshold applies to a hard FM contract?

It depends on the main purpose and the CPV codes. A contract mainly for works uses the works threshold. One mainly for services uses £135,018 for central government or £207,720 for other buyers. Read the tender notice.

Tendarix lists UK public-sector notices from Find a Tender, Contracts Finder and other portals in one search. Browse live notices for construction work, repair and maintenance and design and inspection, or search for facilities management tenders. Then describe your business in the free Tender Fit Report to see the open tenders that match it.