Context
This involves the assurance of Scottish Water's medium-term (SR27) business plan, covering the period from 2027 to 2033. The business plan will set out Scottish Waters investment plans together with the outcomes that we propose to deliver for our customers, communities and the environment, as well as the underlying evidence that we have prepared to support those plans. The information in Scottish Water's business plan submission will be used by the Water Industry Commission Scotland (WICS), Scottish Water's independent economic regulator, in the preparation of its Final Determination. While the business plan is Scottish Water's plan, WICS need to have confidence in the integrity of the data and commentary within it. If WICS have concerns over the impartiality or quality of the assurance report, this would undermine / reduce the value of the assurance to Scottish Water. Therefore, it is essential that the third-party assurance undertaken on the plan is completely impartial.
The timelines for when the assurance work is required is between March and May 2025 for the draft business plan and between October and February 2026 for the final business plan. These dates are fixed due to the submission dates set out by WICS for both plans.
Areas which require assurance are
- Draft and Final Business Plan Data tables, in particular examining whether Scottish Water has prepared these in line both the business plan guidance and definitions set out by WICS and that they are fully consistent with the accompanying commentary prepared by Scottish Water;
- Review of the robustness of the systems and processes used to produce the information;
- Identification of the key assumptions made by Scottish Water in preparing its data tables and review of the reasonableness and materiality of those assumptions; and
- Assurance of the accuracy, completeness and comprehensiveness of the data.
In addition, Scottish Water requires that its independent assurer
- Is able to demonstrate that it is free from any conflicts of interest and/or that where any actual or perceived conflicts of interest may arise as a result of its appointment, that the assurer can put in place measures/arrangements to manage those conflicts of interest for the duration of the appointment;
- Is able to demonstrate the impartiality of its approach to the assurance of the business plan;
- Provides timely efficient feedback on the Draft Business plan to allow Scottish Water to make improvements in its data, evidence and/or processes ahead of the Final Business plan submission;
- Provide draft and final assurance reports to both Scottish Water and Water Industry Commission Scotland (WICS), setting out both the work that has been undertaken, any factors which prevented and/or impeded the assurer from undertaking its role as it might reasonably have expected, and the assurer's findings.
In addition to the above matters, there will be a requirement to engage directly with external stakeholders, including the WICS, to respond to questions on the draft and final assurance reports, including providing further explanation of the assurer's work, findings and/or other matters arising within the terms of reference of their appointment, as is reasonably required.
In order to facilitate the assurer in its role, Scottish Water shall grant the assurors any necessary and timely access to premises, assets, systems, data, working papers, other records and relevant personnel associated with the carrying out of Scottish Water's regulated activities. Scottish Water shall supply the assurors with any information relevant to the assurance process including all material assumptions underpinning the data submission as well as access between the assurors and the financial auditors.
Scottish Water shall not be required to do anything which is outside their control, or to do, or allow the assurors to do, anything which would materially disrupt Scottish Water's business.
Our requirements
The independent assurers should be able to demonstrate a track record in the following areas:
- Independent Third-Party Assurance provision for regulated businesses;
- Assurance for Business Plan submissions for regulated businesses;
- Experience of working with regulated water companies;
- Relevant knowledge of technical, commercial and regulatory aspects of the water sector.
Requirements
In addition to the above matters, there will be a requirement to engage directly with external stakeholders, including the WICS, to respond to questions on the draft and final assurance reports, including providing further explanation of the assurer's work, findings and/or other matters arising within the terms of reference of their appointment, as is reasonably required.
In order to facilitate the assurer in its role, Scottish Water shall grant the assurors any necessary and timely access to premises, assets, systems, data, working papers, other records and relevant personnel associated with the carrying out of Scottish Water's regulated activities. Scottish Water shall supply the assurors with any information relevant to the assurance process including all material assumptions underpinning the data submission as well as access between the assurors and the financial auditors.
Scottish Water shall not be required to do anything which is outside their control, or to do, or allow the assurors to do, anything which would materially disrupt Scottish Water's business.
Submission Instructions
This involves the assurance of Scottish Water's medium-term (SR27) business plan, covering the period from 2027 to 2033. The business plan will set out Scottish Waters investment plans together with the outcomes that we propose to deliver for our customers, communities and the environment, as well as the underlying evidence that we have prepared to support those plans. The information in Scottish Water's business plan submission will be used by the Water Industry Commission Scotland (WICS), Scottish Water's independent economic regulator, in the preparation of its Final Determination. While the business plan is Scottish Water's plan, WICS need to have confidence in the integrity of the data and commentary within it. If WICS have concerns over the impartiality or quality of the assurance report, this would undermine / reduce the value of the assurance to Scottish Water. Therefore, it is essential that the third-party assurance undertaken on the plan is completely impartial.
The timelines for when the assurance work is required is between March and May 2025 for the draft business plan and between October and February 2026 for the final business plan. These dates are fixed due to the submission dates set out by WICS for both plans.
AI AnalysisMembers
Requirements, key tasks and tips for reading this tender — included with Tendarix membership.
£4.99/month after a 7-day free trial. Cancel anytime before it ends and you pay nothing.
Award Details
Binnies UK Limited
Before you bid, buyers check
two years of filed accountsyour financial standingturnover vs contract valueyour Companies House recordcash flow for 30-day termscredit scores and ratios
Actions
Start free trialto open noticeCreate an account and start a 7-day free trial to open the buyer’s own notice and tender documents, plus fit scoring and the Bid Writer. Then £4.99/month — cancel anytime.
Open Bid WriterIndependent software, web & cloud studio. We design, build and grow digital products that quietly outlast their category.
How to Apply
Step-by-step submission guide
Submission Portal
Find a Tender
Open the original notice
Click the button below to view the full notice on Find a Tender Service (FTS)
Check the procedure type
The "Procedure" section tells you if it's Open (one stage) or Restricted (SQ then ITT). This changes how you apply
Access the eSourcing portal
FTS notices link to the buyer's eSourcing platform — register there to access documents
Complete the Selection Questionnaire
Higher-value contracts often require an SQ first — this pre-qualifies you before the full bid stage
Submit electronically
Upload your completed response through the eSourcing platform before the closing date and time
FTS contracts are above UK procurement thresholds. Late submissions are strictly rejected — submit at least 24 hours before the deadline to avoid portal issues.
Buyer Profile
Scottish WaterKey Dates
Published
1 May 2025
Submission deadline
Not specified
Notice type
award
Source
find a tender
Related Tenders
The provision of investment management services for the scottish universities fund ignition strategy
The Bank is seeking proposals from suitably qualified and authorised investment management firms to establish and manage a 15 million GBP segregated investment mandate for the deli
Out of home advertising for bus stations and shelters
Provision of advertising agency services to market, develop and maintain the current and future developed estate within SPT Bus Stations and the SPT Bus Shelter network throughout
Distress brief intervention
North Lanarkshire Council (the "Council") propose to establish a contract with a sole contractor for Distress Brief Intervention. . There is a longstanding culture of joint integra
The provision of community based mental health services incorporating distress brief intervention services level 2
Renfrewshire Council/Renfrewshire Health and Social Care Partnership (RHSCP) are seeking a Provider to deliver a community based mental health service for adults aged over 16 in Re